Aluminum Plant Pipe Cutting

Concrete Cutting & Breaking Sets New Pace at New York Aluminum Plant

What's your best record for concrete cutting? How many lineal feet of concrete can you cut in one day? Concrete Cutting & Breaking, Inc. - Albany, New York recently learned that with a demanding schedule, top-notch operators, and the cooperation and assistance of a capable general contractor, you can rise to this challenge under even the most difficult of circumstances.

Morrison Knudsen, a large General Contractor in the United States, performed hazardous waste remediation work at Alcoa's Massena, New York plant. The goal of this remediation work was to make the plant one of the cleanest, most efficient, most environmentally-safe operations of its kind. The overall budget for this project was $150 million.

Morrison Knudsen's on-site staff spent the cold northern New York winters inside, performing value engineering on the year's upcoming projects. Part of the 1997-98 value engineering effort involved a review of the means and methods which would be used to remediate and upgrade a 60" x 6,154' feet reinforced concrete pipe.

Morrison Knudsen was contracted to expose and open the pipe to determine if damage had occured over the years. Hazardous waste that may have accumulated on the interior pipe walls was to be removed and a durable "sleeve" through the entire pipe length would be installed. In order to accomplish this, MK would have to get inside the pipe.

MK also determined that the most logical means of accessing the pipe's interior would be to sawcut a "cap" off the top of the pipe. The outside diameter of the pipe was 72", with an interior diameter of 60". Looking at the entrance of the pipe as if it were a clock, the decision was made to cut through the entire length of the pipe at the ten o'clock and two o'clock locations.

Several concrete cutting contractors were contacted and asked to provide cost estimates to cut the pipe in the 10 o'clock and 2 o'clock positions. CCB was selected based on their outstanding safety record and sound experience profile.

While the biding process was ongoing, Morrison Kundsen's field crews were experimenting with a walk behind saw and platform. This methodology proved to be quite effective although the working conditions were difficult.

Concrete Cutting & Breaking reviewed the project requirements with the MK officials. Even though the Alcoa plant was 200 miles away from the office, the company dispatched two trucks with equipment and three of CCB's best operators to the job site.

MK's Project Managers had allotted eleven working days for this portion of the project, but CCB would only need eight days to complete their work. In the end, wall sawing proved to be the most efficient and safest means of cutting through the 6" thick concrete pipe. CCB's operators made the two cuts through the pipe, at the prescribed locations, down the entire length of the pipe resulting in a total of 5,000 lineal feet of precision cutting. At 15-foot increments, the operators used hand saws to make cross cuts that allowed MK to remove the concrete cap in manageable segments and gain access to the interior of the pipe. Nearly 1,000 lineal feet of hand sawing was performed to make the cross cuts.

The outstanding efforts from the MK crew with the walk behind saw as well as the remarkable efforts from the CCB crew on the wall saw resulted in the completion of the task for $70,000. This resulted in a projected savings to Alcoa of $70,000 while minimizing the risks associated with the difficult ergonomic conditions of the closed top pipe.

The section of open top pipe received its 36" HDPE slip lining and was ready for its flowable fill encapsulation. The success on the concrete cutting phase of this project was a key element of the project's ongoing success.

 

back to top

   
Related Services
- Wire Sawing

Office
Albany, NY

   

 

Over 5,000 lineal feet of wall sawing and 1,000 feet of hand sawing was necessary to complete remediation work.

 

Wall saw track was set to make the 6" deep cuts.

back to top

Several operators were used each shift to complete the project within its deadline.

 

Wall track was set at 10 o'clock and 2 o'clock positions to remove the top of the pipe.

 

 

back to top