Boston Big Dig Tunnel Project

Concrete Cutting & Breaking Tackles Boston's Big Dig

Boston's Central Artery / Tunnel Project - commonly known as the Big Dig - is the largest, most complex and technologically challenging highway project ever attempted in American history. The project will dramatically reduce traffic and improve mobility in this long-congested city by widening and replacing major portions of highways and subways, most of which are being relocated to tunnels nearly a hundred feet below ground. The Big Dig began in 1991 and will complete sometime in 2004, at a total cost of over $12 billion. It's a project that involves 3.8 million cubic yards of concrete, enough steel rebar to wrap around the earth at the equator, and nearly four thousand workers - including a team of skilled operators from Concrete Cutting and Breaking, Inc. - Boston.

The existing Blue Line Subway Tunnel in Boston is in the process of a complete renovation, lengthening the platform to accommodate six instead of the four subway cars that it now handles. The new tunnel was designed to run north/south, perpendicular to the existing Blue Line that runs east/west. While engineers originally planned the new tunnel to pass above the old tunnel, it was later determined that the new tunnel would have to be lower than expected, placing it on an elevation that would pass through the ceiling of the existing Blue Line. The decision was made to demolish and remove an entire 400 foot section of the old tunnel to accomplish this task.

After discounting implosion of the tunnel due to the fragile foundations of the surrounding buildings, Modern Continental, the General Contractor, contacted CCB to cut and remove the old tunnel. To do this cuts had to be made through the tunnel at 35' intervals so the demolition contractor could have a clean break to finish each weekend. The demolition work was performed exclusively on weekends during which time the entire subway was closed down and reopened for commuter traffic each Monday morning. Conventional demolition was used to remove the tunnel section ends with each designated wire saw line. This ensured that no concrete debris would fall on the tracks below, impeding the scheduled subway service.

The wire sawing task included sawing on one side of the tunnel at track elevation, proceeding to the above archway, and down the opposite side of the tunnel to end at track elevation again. CCB used core holes at each cut location to thread the wire through and performed horizontal wall sawing at the new platform elevation on both sides of the tunnel in designated locations.

CCB was selected for this project by the General Contractor for their ability to provide the timely production schedule that was required to fulfill a tight deadline. Other contractors such as Perini, J.F. White, etc. have also employed CCB to perform other work on the Big Dig.

 

back to top

   
Related Services
- Wire Sawing
- Core Drilling
- Wall Sawing

Office
Boston, MA

   

 

Over 4,000 workers per day are involved in the overall project. When completed in 2004, thousands of cars per hour will be routed through tunnels hundreds of feet under Boston.

 

The Big Dig is the largest construction project in American history.

back to top

Underneath Broad Street, the old subway tunnel's top is cut open.

 

Cutting continues on the subway line under State Street.

 

back to top