Halifax Hospital Core Drilling

Diamond Core Drilling Saves The Day at Halifax Hospital

Concrete Cutting & Breaking, Inc. - Del Ray Beach, Florida - was contracted by Centrex Rodgers Construction, Inc., a large hospital niche contractor, to provide feasible options for the cutting and removal of an abandoned tower crane footing at Halifax Hospital in Daytona Beach, Florida. The need for this job was discovered during an initial site excavation in an open air atrium. During this excavation, it was discovered that the original builders of the hospital had left a tower crane footing which measured 20' by 20' by 4'. This unforeseen obstacle had brought construction to a standstill.

Alternatives for the demolition were examined and diamond cutting was chosen as the best method of controlled demolition. Diamond wire sawing was the method initially selected to expedite this challenging footing removal project. Representatives of Halifax Hospital and Centrex Rodgers Construction, Inc. then met and determined that diamond wire sawing, while the preferred method of demolition, was not "budget friendly" and other alternatives needed to be considered. Line drilling was then proposed as an equally effective and less costly option to sever the footer structure. This technique was ultimately approved.

In addition to budget constraints, line drilling was selected because impact methods could not have been employed due to the confined work area, the close proximity to operational areas , and the possible damaged due to vibrations.

Line drilling a structure of this magnitude within the allotted 10 day time window required precise planning, experienced personnel, and professional drilling equipment. The footer had to be partitioned into 4' by 4' by 4' 6" sections weighing approximately 11,000 lbs. each. Sling holes were required as each piece had to be raised by crane, out of the atrium, and over the existing fully operational emergency room wing of the hospital. The horizontal distance from the center pin to pick point was 93.1 feet. It was calculated that a total of 355 total holes, 6" in diameter and 4' 6" deep, needed to be cut to achieve the necessary dimensions and weights.

Three Diamond Products' 3-phase, 3-speed core drilling units were employed for the duration of the project. Power was supplied from on-board generators. In addition, tube bits measuring 6" diameter by 36" long were instrumental in insuring the success of this project. Three experienced operators drilled approximately 9 hours per day for 10 days to quickly and efficiently section the structure in preparation for removal by crane.

This project utilized diamond tool cutting technologies as opposed to breaking methods. Diamond tool cutting methods once again proved to be effective within the constraints of the project, as well as cost effective. By remaining within budget, allowing undisturbed use of existing facilities, and demonstrating the advantages of today's diamond tool cutting technologies, this project truly demonstrated the advantages of diamond cutting verses alternative and more antiquated breaking methods.

 

 

back to top

   
Related Services
- Core Drilling

Office
Del Ray Beach, FL

   

 

Footing pad before removal of sections.

 

Large sections removed after line drilling.

 

 

back to top