|
Ohio State University
Stadium:
Old Shoe Gets New Soul
Venerable Ohio Stadium in Columbus, Ohio has been the home
of the Ohio State University Buckeyes for over 75 years. "The
Horseshoe", as it is fondly known, has been the scene
of many a collegiate battles over the years. Woody Hayes led
many Buckeye teams to victory and national football championships.
This is the first major renovation ever
done on Ohio Stadium. When completed, The Horseshoe will be
the premier stadium in college football with a seating capacity
of 98,000. The renovation features: increased seating, widened
concourses and aisles, additional restrooms on all levels,
expanded concession areas, increased disability seating, elevators
and escalators to the upper levels and fewer visual obstructions.
While the benefits to the stadium will be
many, one of the main goals was to preserve the look of The
Horseshoe. The stadium will be surrounded with an external
shell but the rotunda and towers at the north, southeast and
southwest sides will all be retained. And the south end will
remain open to preserve the original design configuration.
O'Rourke Wrecking Company of Cincinnati,
Ohio was awarded the $4 million demolition contract at Ohio
Stadium. O'Rourke is a national demolition firm and often
works with concrete cutting companies to facilitate their
projects.
O'Rouke selected Concrete Cutting &
Breaking, Inc. - Columbus, Ohio - because of their reputation
and past work experience. In addition, the scope of the concrete
cutting for this job required the mobilization of a significant
amount of equipment and personnel and CCB could satisfy those
requirements with its Ohio branch locations. "We were
able to pool resources from the Concrete Cutting & Breaking
offices in Columbus, Cleveland and Pittsburgh to meet the
demands of this job" said CCB.
The original contract called for Concrete
Cutting & Breaking to cut 92 sections of A-Deck seats
free. The old A-Deck seats accounted for nearly 40% of the
total stadium seating. Each section of seats consisted of
8 rows of seats, measuring 22' by 18' of 15" thick concrete.
The seat sections weighed 27,000 pounds and were situated
between the 108 rakers. It was decided that four, 2-man crews
working 10-hour shifts for five days per week could complete
this project.
CCB operators first cut the top section
free utilizing push saws with 16" diamond saw blades
to cut to a depth of 5.5". CCB also utilized hydraulic
handsaws manufactured in their own fab shop in Michigan. After
the bottom cut was made, operators used hydraulic wall saws
to cut the sides of the seat sections. Blades with diameters
up to 54 inches were used for this phase of the project. Once
the seat section was cut free, O'Rourke initially lifted out
the seat section with a crane. According to O'Rourke's Project
Manager, "The fragile nature of the 78-year old concrete
necessitated a revised procedure and the sections were instead
lowered to the ground, broken and safely remove."
CCB was employed by O'Rourke to cut 480'
of 3 1/2" - 4" deep cuts on the B-Deck perimeter.
The B-Deck seats were removed on this west side of the stadium
to make room for luxury suites to be installed at a later
date. CCB used a gas powered handsaw with a 16" diameter
diamond blade to make this relatively easy cut. O'Rourke then
used remote breakers to demolish the B-Deck seating. The cutting
on this phase of the project began on November 15, 1999 and,
thanks to the superb team of operators, finished 2 days ahead
of schedule, on December 6, 1999.
Once the seat sections were removed, O'Rourke
planned to remove the cold joint treads and risers on the
top of the rakers with 30 pound chipping hammers. "We
quickly discovered that the treads and risers were part of
a monolithic pour and could not be removed so easily."
In addition, the breakers could have easily damaged the structural
integrity of the rakers and this was not acceptable in this
renovation project. It also presented a major problem as the
replacement precast seat sections were already being fabricated
for installation.
The removal of the treads and risers was
scheduled to be completed by January 15, 2000. O'Rourke called
upon CCB to come to the rescue at The Horseshoe. CCB is often
asked to accept such on-site job challenges. CCB is extremely
innovative and goal oriented in finding solutions to difficult
problems encountered on construction projects. Many of the
CCB operators have graduated from Concrete Sawing and Drilling
Association training programs including Operator Certification,
the highest level of training in the industry.
CCB was able to mobilize 12 operators to
make 17 cuts on each of the 108 rakers, to remove the treads
and risers on the rakers. The weather and operating conditions
proved to be as much a challenge as the job itself. Saw operators
had to mount the wall saw track and conduct the sawing operations
working from lifts. Each raker required 8 vertical cuts and
9 horizontal cuts; the mounting of wall saw track for such
a small cut distance was difficult, especially when working
from a lift platform.
Once the track was in place, the operators
first used 24" diameter by 1/4" wide saw blades
to make the initial cut. Then a 42" diameter wall saw
blade was used to make the final cut to full depth. Diamond
Products wall saw blades were the mainstays for this project.
Because there were to be no overcuts on the rakers, the cut
sections had to be knocked out evenly though they were not
fully cut.
The weather made sawing even more challenging
with subzero temperatures and daily snowfall during this 30-day.
In fact, CCB operators operated in subzero temperatures on
seven of those days and had eight days lost entirely due to
the frigid weather.
The biggest cold weather safety issues of
concern to CCB were cold hands and faces from the extreme
cold weather. Operators were provided with an ample supply
of neoprene gloves and facemasks to minimize cold weather
exposure. To keep the water used to cool the saw blades from
freezing, CCB operators had to maintain a continuous flow
of water, as any type of antifreeze was not accepted on the
construction site. This was even more of a challenge because
there was no source of water on the job site; water was supplied
daily from water tanks on each work truck.
Equipment breakdown also had to be addressed
in this weather. A supply of equipment was maintained in reserve
to allow continuous cutting operations. Even the lifts were
a challenge to keep operating in the subzero weather. CCB
also brought in backup equipment from their office in Buffalo,
New York.
In spite of these challenges the CCB operators
were able to finish the second phase of this $183,000 contract
by the February 15, 2000 completion date. "When we talked
to O'Rourke about doing the Ohio Stadium job, I felt that
we were the best company with the resources and personnel
to effectively complete this job on time" said CCB. "The
saw operators put in 125% on this job and the wealth of experience
from our Cleveland office really helped make a difference
on the Ohio Stadium project."
back to top
|