Power Plant Renovations

One-Inch Clearance Is No Problem In Power Plant Renovation

How do you quickly remove 1.5 million pounds of heavily reinforced concrete located 35 feet above grade, inside an operational power plant, with 1 inch of clearance on four sides? While you're at it, make sure you don't disturb the surrounding steam-turbine generators or interrupt daily production of power.

These were the basic requirements established recently by a Michigan utility company when planning a turbine-generator replacement at a major coal-fired generating plant.

The original 100,000 KW unit was installed in 1944 and operated continuously, except for scheduled maintenance, for the past 54 years. Recently, however, a nearby auto plant created an increased demand for steam, which is a by-product of the generating process. This demand warranted the replacement of the old unit in favor of a more efficient and physically smaller version. Unfortunately, the new unit would not fit the old foundation and necessitated the removal and replacement of the top 8' of concrete.

During the planning and design phase of the project, the consulting engineer brought in Concrete Cutting & Breaking Inc. - Grand Rapids - to help determine the most cost effective and safe method of concrete removal.
Breaking and splitting options were deemed impractical due to the following considerations:

  • Vibration and dust caused by breaking could damage the surrounding machinery and controls.
  • Micro cracking of the concrete caused by breakers was unacceptable in a foundation that was expected to last another 54 years.
  • Potential damage caused by falling debris would create a risk both to surrounding pipes and equipment (some as close as 6 inches), as well as to workers 35 feet below.
  • Debris clean-up costs would be prohibitively expensive and time consuming.

Diamond blade sawing and crushing methods were also dismissed due to the 8' cutting depths required to segment the 85' x 28' monolith.

At the consulting engineers' request, CCB submitted a diamond wire sawing budget, schedule, and schematic for evaluation. Rigging and removal chores were to be handled by the owner's work force using a 200-ton over-head bridge crane. Large pieces were to be cut free, lifted to a modified 12 axle rail car, brought outside, and off-loaded with a 500 ton rental crane.

CCB laid the proposed cuts out in such a way that all the concrete could be continuously cut, shimmed, and left in place prior to the arrival of the rigging crew and equipment. Upon completion, the cutting crew would vacate the site and allow the owner's crew to remove the pieces quickly and safely in one continuous operation. This procedure would minimize the expense of the rental crane, optimize the rigging crew's time, and eliminate the hazard of having the cutters and riggers working in the same place at the same time.

The entire top 8' of the foundation was sectioned into seven pieces weighing up to 130 tons each. In addition there were three smaller pieces that were cut ranging from 4 to 43 tons. Reinforced steel was heavy and the typical 8' x 8' vertical cut contained 106 1-3/8" rods. In addition to the rebar there were also two heavy-flange 24' I-beams embedded in the structure. CCB completed nearly 1,200 square feet of cutting in eleven shifts by utilizing multiple wire saws.

Once the 26' x 8' pieces were cut free, they were ready for removal. To accomplish this lifting maneuver, four 2-1/4" thick steel lugplates were strategically located on each piece for easy removal. Each of the plates were secured by four 1-1/2" diameter rods which were epoxy glued into 1-5/8" x 18" deep holes. The final balancing adjustments were made via 6-foot long turnbuckles. This procedure allowed rigging crews to remove two pieces per shift from the foundation.

CCB was again employed to vertically core drill 215 4" diameter holes 2" deep around the rebar. These holes were made so that a new rod could be welded into place. This project was a good example of how planning can result in a win-win situation for everyone. All the demolition was performed just 20 feet from a control room and 30 feet from a $15 million dollar turbine-generator, without interrupting the everyday operations.

 

back to top

   
Related Services
- Wire Sawing

Office
Grand Rapids, MI

   

 

Wire sawing is used to cut large sections of the foundation.

 

The crane removes a multi-ton section from inside the plant to be cut into smaller pieces.

back to top

Outside crane hoists section.

 

112-ton concrete section removed from plant.

 

back to top