Route 20 Bridge Upgrade

71-Year-Old Bridge Refurbished on Route 20

A good-sized portion of a two-year, $6.6 million, rehabilitation project of a 71-year-old, 415 foot bridge, spanning 18 Mile Creek in Evans, New York was successfully completed recently with the help of Concrete Cutting & Breaking, Inc. - Lancaster, New York.

CCB was awarded this job based on their past history with Oakgrove Construction, as well as for their reputation for large scale projects that require solid planning and methods.

Over thirteen thousand vehicles cross the bridge each day, a traffic load that definitely played a role in the deterioration of the bridge deck. In addition, the age of the bridge itself contributed to its weakened state.

The aggressive project included deck replacement, concrete repairs to the arch ribs, piers and abutments, new architectural panels, coating of all exposed concrete at completion of the work and reconstruction of the immediate roadway approaches. The concrete cutting portion of this job included 96 pillar arch cuts and 26 beam cuts so that the architectural integrity of the bridge could be maintained.

The first half of the project was scheduled to begin at the center span of the bridge where the deck and floorbeams were to be removed so that the columns and arches could be exposed. Repairs, if needed, were to be made and then the bridge deck installed.

Prior to cutting, a working platform was constructed and placed approximately 2 feet below the pier cuts. The first cutting performed was the vertical beam cuts. This required two saws cutting simultaneously between each pier as a crane held each beam with just enough tension from above. The job required the cutting to be done from both sides of each beam.

On each beam removal, a #11 reinforcement bar was left uncut to prevent the piece of concrete from moving and slamming the blades; the rebar was torched after the cutting was completed. The beam was then lifted by the crane and lowered to the ground 90 feet below. CCB then mounted the wall saws on the arches. This cutting also required that each arch be double cut and held in place by the crane, due to excessive pressure and movement in the bridge structure. The final cutting was the horizontal pier cuts, also requiring saw cuts from both sides and the crane providing tension to prevent the blades from slamming.

As the large concrete sections of the bridge were removed, they had to be immediately replaced with the new, keeping the same weight load and structural integrity of the bridge at all times. The prevented cracking of the existing bridge structure that was to remain.

A large quantity of structural concrete had to be removed in a short period of time. Access also proved to be quite difficult as the bridge stands 90 feet above the creek. The bottom portions of the bridge could not be damaged during the job, nor could debris fall into the water or creek bed below. In addition, one large crane was used instead of multiple pieces of equipment, so the planning for the removal phase of the project had to take this into consideration.

Today, thanks to CCB, thousands of cars once again flow across this historic bridge.

 

back to top

   
Related Services
- Highway
- Slab Sawing

Office
Lancaster, NY

   

 

Bridge deck and floor beams were slab sawed for removal.

 

 

Large sections were removed by crane to be lowered to the creek bottom below.

back to top