|
Sea World Saved with Life Support
System Rehabilitation
The Williams Company, a general contractor
from Orlando, Florida, was awarded the contract to completely
remove and replace all concrete structures associated with
Sea World's Life Support systems. This structure was constructed
as an integral and original portion of the park's salt water
exhibit filtration system. Over time, salt water intrusion
through the tank walls and tank slab oxidized the reinforcing
steel, weakening and deteriorating the perimeter walls and
tank slab. Certain portions of the tank walls were bowed up
to 12" from centerline and were braced by flying buttresses.
Water loss in the range of thousands
of gallons from this deterioration prompted Sea World to replace
the leaking tank. All water for the animal attractions (including
Shamu, dolphins, sea lions, tropical fish and outdoor animal
exhibits) is filtered and oxygenated by way of the Life Support
System facilities. This is an un-interruptible and critical
process; without it the park could not function. Any system
failure, pipe breakage, or tank-wall failure could spell disaster.
These parameters along with extremely
confined work areas created a unique situation for Concrete
Cutting & Breaking Inc. - Orlando, Florida. Because the
structure was deteriorated and the support system had to remain
operational during the selective demolition, the use of diamond
cutting was ideal. The fragile support systems had to be worked
around delicately. The fact that diamond sawing generates
little vibration and little dust made CCB a necessary part
of the controlled demolition.
CCB and The Williams Company engineered
a selective demolition schedule to quickly complete this massive
structure removal as safe and controlled as possible. Contamination
of processed water adjacent to the work area by dust or debris
was unacceptable. After two of the four tanks were drained
and cleaned, CCB began by wall sawing a man door through the
16" double mat #8 reinforced tank wall to allow easy
access to the tanks' interior. Scaffolding was erected and
four 6" sling holes per section were drilled for crane
removal.
To expedite removal, entire perimeter
sections of the wall, up to 100' in length, were braced and
wall sawed. Approximately 17' by 16' by 16' pieces were lifted
to a staging area to be slab sawed into 8' by 6' by 16"
pieces and removed to an off-site location. Three wall saws
with Diamond Products split-segment blades were used to maintain
a production rate compatible with the General Contractor's
completion schedule. After all the wall sections were removed,
slab sawing of the tank bottom commenced. Two Core Cut 65hp
slab saws and one CCB parapet slab saw were used to section
the tank bottom into 7' by 5' by 22" pieces.
Original blueprints indicated a double
mat of #8 rebar at 16" center but the actual field varied
greatly from these specifications. Actual steel placement
was top mat of #10 rebar at 6" centers going in both
directions and a bottom mat of #8 at 16" centers going
both directions. After the discovery of a substantial amount
of rebar in bottom of the tank slab, CCB mobilized a Vermeer
trencher and a pair of CCB parapet slab saws with 60"
diameter blades to tackle the overly-thick areas. With the
unprecedented amount of rebar, the epoxy bottom coating, and
leaking walls in adjacent tanks, this task was by no means
routine.
Due to the deterioration of the tank
walls, it was determined that sawing was not an option. Therefore
Bristar, a chemical expansion material, was used. The first
basin was drilled, filled with Bristar, and set up overnight.
The chemical successfully fractured the unreinforced structures
sufficiently for removal.
Throughout the project, CCB perfomed:
- 230 6" by 16" sling holes
- 1950' of 16" tank wall sawing
- 500' of 8" tank wall sawing
- 2900' of 24" tank slab sawing
- 1500' of 16" wall sections
- 600' of 8" wall sections
CCB and The Williams Company performed
this challenging twelve-month demolition project professionally
and within the parameters unique to the jobsite.
back to top
|
 |
| Concrete
Cutting and Breaking's challenge was to remove Sea World's
original water filtration tanks without disturbing the
park's delicate ecosystem. |
 |
| Wall
sawing tank sections for removal by crane. |
 |
| A
CCB Parapet Saw with 60" blade was used to achieve cut
depths of 27". |
back to top
|